This project is eliminated from views and totals because it will be deactivated due to migration in the Development and Cohesion Plan.
Updated on 31/12/2022
Funding monitored € 47,131.15 of which cohesion funds € 47,131.15
Given name Amount
Development and Cohesion Fund47131.15
Economies:
€ 10,368.85
Payments monitored € 11,500.00 of which cohesion funds € 11,500.00
Year Amount Cumulative amount Percentage on public financing
202011500.0011500.0024

State of progress

Open
Expected start: 21/06/2019
Effective start: not available
Expected end: 31/12/2020
Effective end: not available

Type

  • Infrastructure
  • MANUTENZIONE STRAORDINARIA DI ADEGUAMENTO IMPIANTISTICA E O ANTINCENDIO

Theme

Territory

Entities

Planning body
MIUR ISTRUZIONE
Implementing body
COMUNE DI PALAZZOLO ACREIDE
Beneficiary
COMUNE DI PALAZZOLO ACREIDE
Executor
COMUNE DI PALAZZOLO ACREIDE
Priority QSN
Miglioramento e valorizzazione delle risorse umane
General objective QSN
Innalzare i livelli di apprendimento e di competenze chiave, l'effettiva equità di accesso ai percorsi migliori, aumentare la copertura dei percorsi di istruzione e formazione iniziale
Specific objective QSN
Accrescere il tasso di partecipazione all'istruzione e formazione iniziale

Programming area

Programme
PROGRAMMA ATTUATIVO MIUR MESSA IN SICUREZZA EDIFICI SCOLASTICI
2007-2013 National Development and Cohesion Fund
2007-2013 National Development and Cohesion Fund
Cohesion funds
€ 47,131.15
Payments on cohesion funds
€ 11,500.00
Line
Riqualificazione e messa in sicurezza delle istituzioni scolastiche statali
Action
ulteriori interventi finanziabili ai sensi art. 18 DL 69/2013

Other projects in territory