CUP: E54H14000600001
INTERVENTI FINALIZZATI ALL'INNALZAMENTO DEL LIVELLO DI SICUREZZA DELL'EDIFICIO SEDE DELLA SCUOLA ELEMENTARE E MEDIA
Download project
This project is eliminated from views and totals because it is a duplicate of the project:
Funding monitored
€ 321,958.59
of which cohesion funds
€ 321,958.59
Given name | Amount |
---|---|
Development and Cohesion Fund | 321958.59 |
- Economies:
- € 12,952.63
Payments monitored
€ 321,958.59
of which cohesion funds
€ 321,958.59
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2015 | 321958.59 | 321958.59 | 100 |
State of progress
Completed
Expected start: 25/06/2015
Effective start: 25/06/2015
Expected end: 04/09/2015
Effective end: 05/09/2015
Type
- Infrastructure
- MANUTENZIONE STRAORDINARIA
Theme
- Education and training
- Infrastrutture per l'istruzione
Territory
Entities
- Planning body
- MIUR ISTRUZIONE
- Implementing body
- COMUNE DI TORO
- Beneficiary
- COMUNE DI TORO
- Executor
- COMUNE DI TORO
- Priority QSN
- Miglioramento e valorizzazione delle risorse umane
- General objective QSN
- Innalzare i livelli di apprendimento e di competenze chiave, l'effettiva equità di accesso ai percorsi migliori, aumentare la copertura dei percorsi di istruzione e formazione iniziale
- Specific objective QSN
- Accrescere il tasso di partecipazione all'istruzione e formazione iniziale
Programming area
- 2007-2013 National Development and Cohesion Fund
- 2007-2013 National Development and Cohesion Fund
- Programme
- PROGRAMMA ATTUATIVO MIUR MESSA IN SICUREZZA EDIFICI SCOLASTICI
- Line
- Riqualificazione e messa in sicurezza delle istituzioni scolastiche statali
- Action
- ulteriori interventi finanziabili ai sensi art. 18 DL 69/2013