CUP: G38G10001680007
SOSTITUZIONE CENTRALE TERMICA/ISOLAMENTO TERMICO/IMPIANTO GEOTERMICO
Download project
Funding monitored
€ 241,044.29
of which cohesion funds
€ 241,044.29
Given name | Amount |
---|---|
European Union | 180783.21 |
Revolving Fund (National co-financing) | 60261.08 |
- Economies:
- € 4,003.62
Payments monitored
€ 241,044.29
of which cohesion funds
€ 241,044.29
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2014 | 225.00 | 225.00 | 0 |
2015 | 240819.29 | 241044.29 | 100 |
State of progress
Completed
Expected start: 18/09/2012
Effective start: 18/09/2012
Expected end: 18/09/2013
Effective end: 18/12/2015
Type
- Infrastructure
- MANUTENZIONE STRAORDINARIA
Theme
- Education and training
- Infrastrutture per l'istruzione
Territory
Entities
- Planning body
- MINISTERO DELL'ISTRUZIONE E DEL MERITO
- Implementing body
- I.C. G.PASCOLI
- Priority QSN
- Miglioramento e valorizzazione delle risorse umane
- General objective QSN
- Innalzare i livelli di apprendimento e di competenze chiave, l'effettiva equità di accesso ai percorsi migliori, aumentare la copertura dei percorsi di istruzione e formazione iniziale
- Specific objective QSN
- Innalzare i livelli medi dell'apprendimento, promuovere le eccellenze e garantire un livello minimo di competenze per tutti
Programming area
- Programme
- ROP CONV ERDF CAMPANIA
- European Regional Development Fund (ERDF)
- 2007-2013 EU Structural Funds
- Cohesion funds
- € 241,044.29
- Payments on cohesion funds
- € 241,044.29
- Axis
- Sviluppo urbano e qualità della vita
- Operational objective
- CITTA' SOLIDALI E SCUOLE APERTE.
Other projects in territory
Same theme
Isolamento Termico/Impianto fotovoltaico | € 226,310 |
LIM e didattica innovativa | € 74,349 |
Informatic@scuola | € 71,767 |
Realizzazione corpo ascensore | € 67,523 |
SOSTITUZIONE INFISSI ESTERNI/PORTE INTERNE/ADEGUAMENTO SERVIZI IGIENICI | € 62,480 |