CUP: H19H13000090001
LAVORI DI SOVRALZO E RINGROSSO CON ADEGUAMENTO DELLA DIFESA DELL'ARGINE DESTRO DEL FIUME BACCHIGLIONE FRA LOCALITA DEBBA E COL DE RUGA IN COMUNE DI LONGARE 2 STRALCIO COMPLETAMENTO
Download project
Funding monitored
€ 1,038,000.00
of which cohesion funds
€ 1,038,000.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 1038000.00 |
Payments monitored
€ 1,024,336.09
of which cohesion funds
€ 1,024,336.09
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2016 | 869218.24 | 869218.24 | 83 |
2017 | 7102.48 | 876320.72 | 84 |
2018 | 48108.88 | 924429.60 | 89 |
2019 | 79676.24 | 1004105.84 | 96 |
2020 | 20230.25 | 1024336.09 | 98 |
State of progress
Completed
Expected start: 10/08/2015
Effective start: 10/08/2015
Expected end: 03/03/2020
Effective end: 03/03/2020
Type
- Infrastructure
- MANUTENZIONE STRAORDINARIA
Theme
- Environment
- Prevenzione dei rischi (inclusa elaborazione e attuazione di piani e provvedimenti))
Territory
Entities
- Planning body
- REGIONE DEL VENETO
- Implementing body
- REGIONE DEL VENETO
- Beneficiary
- REGIONE DEL VENETO
- Priority QSN
- Energia e ambiente: uso sostenibile e efficiente delle risorse per lo sviluppo
- General objective QSN
- Garantire le condizioni di sostenibilità ambientale dello sviluppo e livelli adeguati di servizi ambientali per la popolazione e le imprese
- Specific objective QSN
- Accrescere la capacità di offerta, la qualità e l'efficienza del servizio idrico, e rafforzare la difesa del suolo e la prevenzione dei rischi naturali
Programming area
- 2007-2013 National Development and Cohesion Fund
- 2007-2013 National Development and Cohesion Fund
- Programme
- PROGRAMMA NAZIONALE DI ATTUAZIONE (PNA) FSC RISANAMENTO AMBIENTALE
- Line
- Interventi di risanamento ambientale Regione Veneto
- Action
- AP per la mitigazione del rischio idrogeologico Regione Veneto