CUP: H59G04000050001
VALLE DEI MOLINI. INTEGRAZIONE SISTEMAZIONI ESISTENTI CON BRIGLIE DI NOTEVOLI DIMENSIONI E ALTRE OPERE DI SISTEMAZIONE ONDE STABILIZZARE IL FONDO DELL'ALVEO.
SUMMARY OF THE PROJECT
VALLE DEI MOLINI. INTEGRAZIONE SISTEMAZIONI ESISTENTI CON BRIGLIE DI NOTEVOLI DIMENSIONI E ALTRE OPERE DI SISTEMAZIONE ONDE STABILIZZARE IL FONDO DELL'ALVEO.
Implementation indicator
Estensione in lunghezza
- Target
- 0.64 km
- Achieved
- 0.64 km
Download project
Funding monitored
€ 1,997,957.03
of which cohesion funds
€ 1,997,957.03
Given name | Amount |
---|---|
Development and Cohesion Fund | 1997957.03 |
Payments monitored
€ 1,994,411.50
of which cohesion funds
€ 1,994,411.50
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2004 | 116615.52 | 116615.52 | 5 |
2005 | 642835.02 | 759450.54 | 38 |
2006 | 891158.87 | 1650609.41 | 82 |
2007 | 321736.19 | 1972345.60 | 98 |
2008 | 990.14 | 1973335.74 | 98 |
2009 | 12147.98 | 1985483.72 | 99 |
2010 | 0 | 1985483.72 | 99 |
2011 | 0 | 1985483.72 | 99 |
2012 | 0 | 1985483.72 | 99 |
2013 | 0 | 1985483.72 | 99 |
2014 | 0 | 1985483.72 | 99 |
2015 | 0 | 1985483.72 | 99 |
2016 | 0 | 1985483.72 | 99 |
2017 | 0 | 1985483.72 | 99 |
2018 | 8927.78 | 1994411.50 | 99 |
State of progress
Completed
Expected start: 15/06/2005
Effective start: 15/06/2005
Expected end: 21/09/2007
Effective end: 21/09/2007
Entities
- Planning body
- REGIONE DEL VENETO
- Implementing body
- REGIONE DEL VENETO
- Beneficiary
- REGIONE DEL VENETO
Programming area
- Programme
- PSC REGIONE VENETO
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Cohesion funds
- € 1,997,957.03
- Payments on cohesion funds
- € 1,994,411.50
- Policy Area
- Ambiente e risorse naturali
- Sector of intervention
- Rischi e adattamento climatico