CUP: B75H05000110002
Interventi per la mitigazione del rischio del bacino Ramostorto
SUMMARY OF THE PROJECT
Interventi per la mitigazione del rischio del bacino Ramostorto
Implementation indicator
Non richesto (Migrazione PSC)
- Target
- 0.01 num
- Achieved
- 0.01 num
Download project
Funding monitored
€ 1,508,242.55
of which cohesion funds
€ 1,500,000.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 1500000.00 |
Another public source | 8242.55 |
Payments monitored
€ 1,508,242.55
of which cohesion funds
€ 1,499,999.99
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2006 | 238046.40 | 238046.40 | 15 |
2007 | 891463.87 | 1129510.27 | 74 |
2008 | 99726.77 | 1229237.04 | 81 |
2009 | 126779.93 | 1356016.97 | 89 |
2010 | 152225.58 | 1508242.55 | 100 |
State of progress
Completed
Expected start: 13/09/2006
Effective start: 13/09/2006
Expected end: 27/03/2009
Effective end: 27/03/2009
Entities
- Planning body
- CONSORZIO DI BONIFICA ADIGE PO
- Implementing body
- CONSORZIO DI BONIFICA ADIGE PO
- Beneficiary
- CONSORZIO DI BONIFICA ADIGE PO
Programming area
- Programme
- PSC REGIONE VENETO
- Fondo Aree Sottoutilizzate 2000-2006
- 2000-2006 Underutilized Areas Fund
- Cohesion funds
- € 1,500,000.00
- Payments on cohesion funds
- € 1,499,999.99
- Policy Area
- Ambiente e risorse naturali
- Sector of intervention
- Rischi e adattamento climatico