CUP: H88B04000010001
OPERE DI RITENUTA SUL TORRENTE BIOS A MONTE DI CENCENIGHE E SISTEMAZIONE DEL TORRENTE GAVONE
SUMMARY OF THE PROJECT
OPERE DI RITENUTA SUL TORRENTE BIOS A MONTE DI CENCENIGHE E SISTEMAZIONE DEL TORRENTE GAVONE
Implementation indicator
Estensione in lunghezza
- Target
- 0.50 km
- Achieved
- 0.50 km
Funding monitored
€ 1,352,737.44
of which cohesion funds
€ 1,352,737.44
Given name | Amount |
---|---|
Development and Cohesion Fund | 1352737.44 |
Payments monitored
€ 1,352,737.44
of which cohesion funds
€ 1,352,737.44
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2004 | 36573.60 | 36573.60 | 2 |
2005 | 31194.99 | 67768.59 | 5 |
2006 | 21719.96 | 89488.55 | 6 |
2007 | 22807.61 | 112296.16 | 8 |
2008 | 4230.00 | 116526.16 | 8 |
2009 | 7796.13 | 124322.29 | 9 |
2010 | 690023.20 | 814345.49 | 60 |
2011 | 255532.39 | 1069877.88 | 79 |
2012 | 248198.84 | 1318076.72 | 97 |
2013 | 9078.53 | 1327155.25 | 98 |
2014 | 14175.12 | 1341330.37 | 99 |
2015 | 11407.07 | 1352737.44 | 100 |
State of progress
Completed
Expected start: 15/09/2008
Effective start: 15/09/2008
Expected end: 31/12/2011
Effective end: 08/11/2011
Entities
- Planning body
- REGIONE DEL VENETO
- Implementing body
- REGIONE DEL VENETO
- Beneficiary
- REGIONE DEL VENETO
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- PSC REGIONE VENETO
- Policy Area
- Ambiente e risorse naturali
- Sector of intervention
- Rischi e adattamento climatico