CUP: H59J14000520006
SISTEMAZIONE E RIORDINO DI PIAZZA SAN MARCO CON ADEGUAMENTO SPAZI E VIABILITA' - SECONDO STRALCIO
SUMMARY OF THE PROJECT
SISTEMAZIONE E RIORDINO DI PIAZZA SAN MARCO CON ADEGUAMENTO SPAZI E VIABILITA' - SECONDO STRALCIO
Implementation indicator
Superficie oggetto di intervento
- Target
- 2,500 mq
- Achieved
- 2,500 mq
Funding monitored
€ 374,672.97
of which cohesion funds
€ 281,004.73
Given name | Amount |
---|---|
Development and Cohesion Fund | 281004.73 |
Municipality | 93668.24 |
Payments monitored
€ 374,672.97
of which cohesion funds
€ 281,004.73
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2015 | 21295.20 | 21295.20 | 5 |
2016 | 346757.97 | 368053.17 | 98 |
2017 | 6619.80 | 374672.97 | 100 |
State of progress
Completed
Expected start: 07/03/2016
Effective start: 07/03/2016
Expected end: 26/09/2016
Effective end: 26/09/2016
Entities
- Planning body
- COMUNE DI PIEVE DEL GRAPPA
- Implementing body
- COMUNE DI PIEVE DEL GRAPPA
- Beneficiary
- COMUNE DI PIEVE DEL GRAPPA
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- PSC REGIONE VENETO
- Policy Area
- Riqualificazione urbana
- Sector of intervention
- Edilizia e spazi pubblici