CUP: C61B14000470006
PERCORSO CICLO-PEDONALE VIA CAMPET, DI ACCESSO AL COMPLESSO CANOVIANO
SUMMARY OF THE PROJECT
PERCORSO CICLO-PEDONALE VIA CAMPET, DI ACCESSO AL COMPLESSO CANOVIANO
Implementation indicator
Estensione in lunghezza
- Target
- 1.20 km
- Achieved
- 1.20 km
Funding monitored
€ 389,776.35
of which cohesion funds
€ 309,530.34
Given name | Amount |
---|---|
Development and Cohesion Fund | 309530.34 |
Municipality | 80246.01 |
Payments monitored
€ 389,776.35
of which cohesion funds
€ 309,530.34
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2016 | 162782.48 | 162782.48 | 41 |
2017 | 226993.87 | 389776.35 | 100 |
State of progress
Completed
Expected start: 18/07/2016
Effective start: 25/07/2016
Expected end: 30/09/2017
Effective end: 30/09/2017
Entities
- Planning body
- REGIONE DEL VENETO
- Implementing body
- COMUNE DI POSSAGNO
- Beneficiary
- COMUNE DI POSSAGNO
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- PSC REGIONE VENETO
- Policy Area
- Riqualificazione urbana
- Sector of intervention
- Edilizia e spazi pubblici
Other projects in territory
Same type of investment
BANDA ULTRALARGA NELLE AREE BIANCHE DEL TERRITORIO DELLA REGIONE VENETO CON FONDI FSC | € 47,460,207 |