CUP: I72C14000020005
Lavori di completamento, conservazione e restauro di Palazzo Sturm
SUMMARY OF THE PROJECT
Lavori di completamento, conservazione e restauro di Palazzo Sturm
Implementation indicator
Superficie oggetto di intervento
- Target
- 185 mq
- Achieved
- 186 mq
Download project
Funding monitored
€ 1,354,416.21
of which cohesion funds
€ 934,080.14
Given name | Amount |
---|---|
Development and Cohesion Fund | 934080.14 |
Municipality | 420336.07 |
Payments monitored
€ 1,354,416.21
of which cohesion funds
€ 934,080.12
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2016 | 74224.14 | 74224.14 | 5 |
2017 | 267366.37 | 341590.51 | 25 |
2018 | 739096.19 | 1080686.70 | 79 |
2019 | 153423.74 | 1234110.44 | 91 |
2020 | 56785.04 | 1290895.48 | 95 |
2021 | 63520.73 | 1354416.21 | 100 |
State of progress
Completed
Expected start: 20/03/2017
Effective start: 19/04/2017
Expected end: 31/03/2021
Effective end: 31/03/2021
Entities
- Planning body
- REGIONE DEL VENETO
- Implementing body
- REGIONE DEL VENETO
- Beneficiary
- REGIONE DEL VENETO
Programming area
- Programme
- PSC REGIONE VENETO
- 2007-2013 National Development and Cohesion Fund
- 2007-2013 National Development and Cohesion Fund
- Cohesion funds
- € 934,080.14
- Payments on cohesion funds
- € 934,080.12
- Policy Area
- Cultura
- Sector of intervention
- Patrimonio e paesaggio