CUP: B64H14001690002
INTERVENTI DI RIPRESA DI FRANE E MESSA IN SICUREZZA DEL FIUME TRIBOLO FINALIZZATI ALLA RIDUZIONE DEL RISCHIO IDRAULICO NEI COMUNI DI MONTICELLO CONTE OTTO, BOLZANO VICENTINO, QUINTO VICENTINO E VICENZA, GRAVEMENTE COLPITI DAGLI EVENTI DIPIENA DEL 1.11.2010 E 11.11.2012
SUMMARY OF THE PROJECT
INTERVENTI DI RIPRESA DI FRANE E MESSA IN SICUREZZA DEL FIUME TRIBOLO FINALIZZATI ALLA RIDUZIONE DEL RISCHIO IDRAULICO NEI COMUNI DI MONTICELLO CONTE OTTO, BOLZANO VICENTINO, QUINTO VICENTINO E VICENZA, GRAVEMENTE COLPITI DAGLI EVENTI DIPIENA DEL 1.11.2010 E 11.11.2012
Implementation indicator
Non richesto (Migrazione PSC)
- Target
- 0.01 num
- Achieved
- 0.01 num
Funding monitored
€ 723,211.23
of which cohesion funds
€ 723,211.23
Given name | Amount |
---|---|
Development and Cohesion Fund | 723211.23 |
Payments monitored
€ 723,211.23
of which cohesion funds
€ 723,211.23
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2017 | 341402.77 | 341402.77 | 47 |
2018 | 373561.43 | 714964.20 | 98 |
2019 | 8247.03 | 723211.23 | 100 |
State of progress
Completed
Expected start: 02/03/2017
Effective start: 23/02/2017
Expected end: 26/11/2018
Effective end: 12/04/2018
Entities
- Planning body
- REGIONE DEL VENETO
- Implementing body
- REGIONE DEL VENETO
- Beneficiary
- REGIONE DEL VENETO
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- PSC REGIONE VENETO
- Policy Area
- Ambiente e risorse naturali
- Sector of intervention
- Rischi e adattamento climatico