Lavori di messa in sicurezza delle arginature in sinistra Po in Comune di Ficarolo (RO) - I fase - I stralcio funzionale
SUMMARY OF THE PROJECT
Lavori di messa in sicurezza delle arginature in sinistra Po in Comune di Ficarolo (RO) - I fase - I stralcio funzionale
Implementation indicator
Non richesto (Migrazione PSC)
- Target
- 0.01 num
- Achieved
- 0.01 num
Download project
Funding monitored
€ 978,766.30
of which cohesion funds
€ 978,766.30
Given name | Amount |
---|---|
Development and Cohesion Fund | 978766.30 |
Payments monitored
€ 978,766.30
of which cohesion funds
€ 978,766.30
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2011 | 49836.43 | 49836.43 | 5 |
2012 | 0 | 49836.43 | 5 |
2013 | 0 | 49836.43 | 5 |
2014 | 0 | 49836.43 | 5 |
2015 | 0 | 49836.43 | 5 |
2016 | 15729.21 | 65565.64 | 6 |
2017 | 771303.53 | 836869.17 | 85 |
2018 | 139430.01 | 976299.18 | 99 |
2019 | 0 | 976299.18 | 99 |
2020 | 0 | 976299.18 | 99 |
2021 | 2467.12 | 978766.30 | 100 |
State of progress
Completed
Expected start: 01/10/2017
Effective start: 02/03/2017
Expected end: 31/12/2017
Effective end: 04/10/2017
Entities
- Planning body
- REGIONE DEL VENETO
- Implementing body
- REGIONE DEL VENETO
- Beneficiary
- REGIONE DEL VENETO
Programming area
- Programme
- PSC REGIONE VENETO
- 2007-2013 National Development and Cohesion Fund
- 2007-2013 National Development and Cohesion Fund
- Cohesion funds
- € 978,766.30
- Payments on cohesion funds
- € 978,766.30
- Policy Area
- Ambiente e risorse naturali
- Sector of intervention
- Rischi e adattamento climatico