CUP: J54E21000160001
8.1 Assistenza tecnica nellattuazione e monitoraggio della Strategia
SUMMARY OF THE PROJECT
Assistenza tecnica nellattuazione e monitoraggio della Strategia
Implementation indicator
Analisi, studi e progettazioni
- Target
- 4 num
- Achieved
- 0 num
Download project
Funding monitored
€ 160,760.00
of which cohesion funds
€ 160,760.00
Given name | Amount |
---|---|
Revolving Fund | 160760.00 |
Payments monitored
€ 32,436.75
of which cohesion funds
€ 32,436.75
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2023 | 19462.05 | 19462.05 | 12 |
2024 | 12974.70 | 32436.75 | 20 |
State of progress
Open
Expected start: 11/11/2022
Effective start: 11/11/2022
Expected end: 11/11/2025
Effective end: not available
Entities
- Planning body
- REGIONE DEL VENETO
- Implementing body
- UNIONE MONTANA AGORDINA
- Beneficiary
- UNIONE MONTANA AGORDINA
Programming area
- Programme
- STRATEGIA AREE INTERNE REGIONE VENETO SERVIZI
- Ordinary resources
- Risorse nazionali ordinarie
- Cohesion funds
- € 160,760.00
- Payments on cohesion funds
- € 32,436.75
- Internal Area
- Area Interna Unione Montana Agordina
- Scope of action
- Assistenza Tecnica