Updated on 30/04/2025
Funding monitored € 555,714.39 of which cohesion funds € 333,428.63
Given name Amount
Development and Cohesion Fund333428.63
Municipality222285.76
Payments monitored € 555,714.39 of which cohesion funds € 333,428.63
Year Amount Cumulative amount Percentage on public financing
2016228225.02228225.0241
201751040.21279265.2350
2018276449.16555714.39100

State of progress

Completed
Expected start: 29/06/2016
Effective start: 29/06/2016
Expected end: 30/11/2016
Effective end: 29/11/2016

Type

  • Infrastructure
  • MANUTENZIONE STRAORDINARIA CON EFFICIENTAMENTO ENERGETICO

Theme

Territory

Entities

Planning body
REGIONE DEL VENETO
Implementing body
COMUNE DI VILLANOVA DEL GHEBBO
Beneficiary
COMUNE DI VILLANOVA DEL GHEBBO

Programming area

Programme
PSC REGIONE VENETO
2007-2013 National Development and Cohesion Fund
2007-2013 National Development and Cohesion Fund
Cohesion funds
€ 333,428.63
Payments on cohesion funds
€ 333,428.63
Policy Area
Energia
Sector of intervention
Efficienza energetica

Other projects in territory