CUP: E64E04000050001
EX S.S. 3 VIA 'FLAMINIA': ELIMINAZIONE DEGLI INCROCI A RASO MEDIANTE COSTRUZIONE DI DUE SVINCOLI E L'ADEGUAMENTO DELLA VIABILITA ESISTENTE TRA I KM 155+100 E KM 159+000.
SUMMARY OF THE PROJECT
EX S.S. 3 VIA 'FLAMINIA': ELIMINAZIONE DEGLI INCROCI A RASO MEDIANTE COSTRUZIONE DI DUE SVINCOLI E L'ADEGUAMENTO DELLA VIABILITA ESISTENTE TRA I KM 155+100 E KM 159+000.
Implementation indicator
Estensione in lunghezza
- Target
- 5 km
- Achieved
- 5 km
Download project
Funding monitored
€ 24,835,063.52
of which cohesion funds
€ 5,435,063.52
Given name | Amount |
---|---|
Development and Cohesion Fund | 5435063.52 |
Another public source | 19400000.00 |
Payments monitored
€ 21,158,724.95
of which cohesion funds
€ 4,630,510.13
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2011 | 0.01 | 0.01 | 0 |
2012 | 493089.55 | 493089.56 | 1 |
2013 | 1398331.06 | 1891420.62 | 7 |
2014 | 3571921.36 | 5463341.98 | 21 |
2015 | 3441709.43 | 8905051.41 | 35 |
2016 | 1157320.86 | 10062372.27 | 40 |
2017 | 1136865.07 | 11199237.34 | 45 |
2018 | 2881995.60 | 14081232.94 | 56 |
2019 | 6934709.70 | 21015942.64 | 84 |
2020 | 142782.31 | 21158724.95 | 85 |
State of progress
Open
Expected start: 08/08/2012
Effective start: 08/08/2012
Expected end: 22/03/2019
Effective end: 22/03/2019
Entities
- Planning body
- QUADRILATERO MARCHE UMBRIA SPA
- Implementing body
- QUADRILATERO MARCHE UMBRIA SPA
- Beneficiary
- QUADRILATERO MARCHE UMBRIA SPA
- Executor
- QUADRILATERO MARCHE UMBRIA SPA
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- PSC REGIONE UMBRIA
- Policy Area
- Trasporti e Mobilita'
- Sector of intervention
- Trasporto stradale