CUP: E63B05000100001
INTERVENTI DIRETTI ALLA RIDUZIONE DEL RISCHIO IDRAULICO E AL RISANAMENTO AMBIENTALE NEI BACINI DEL FIUME TOPINO E TORR. CHIONA
SUMMARY OF THE PROJECT
INTERVENTI DIRETTI ALLA RIDUZIONE DEL RISCHIO IDRAULICO E AL RISANAMENTO AMBIENTALE NEI BACINI DEL FIUME TOPINO E TORR. CHIONA
Download project
Funding monitored
€ 8,749,444.35
of which cohesion funds
€ 8,232,987.52
Given name | Amount |
---|---|
Development and Cohesion Fund | 8232987.52 |
Another public source | 516456.83 |
Payments monitored
€ 8,749,444.35
of which cohesion funds
€ 8,232,987.52
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2001 | 2465.36 | 2465.36 | 0 |
2002 | 0 | 2465.36 | 0 |
2003 | 34572.45 | 37037.81 | 0 |
2004 | 0 | 37037.81 | 0 |
2005 | 302361.70 | 339399.51 | 3 |
2006 | 22041.80 | 361441.31 | 4 |
2007 | 42228.00 | 403669.31 | 4 |
2008 | 3137.34 | 406806.65 | 4 |
2009 | 0 | 406806.65 | 4 |
2010 | 52590.16 | 459396.81 | 5 |
2011 | 1753305.45 | 2212702.26 | 25 |
2012 | 2363229.89 | 4575932.15 | 52 |
2013 | 506278.36 | 5082210.51 | 58 |
2014 | 782593.40 | 5864803.91 | 67 |
2015 | 328683.53 | 6193487.44 | 70 |
2016 | 1070140.37 | 7263627.81 | 83 |
2017 | 570412.23 | 7834040.04 | 89 |
2018 | 61225.48 | 7895265.52 | 90 |
2019 | 854178.83 | 8749444.35 | 100 |
State of progress
Completed
Expected start: 23/12/2010
Effective start: 23/12/2010
Expected end: 14/02/2018
Effective end: 14/02/2018
Entities
- Planning body
- REGIONE UMBRIA
- Implementing body
- CONSORZIO BONIFICAZIONE UMBRA
- Beneficiary
- CONSORZIO BONIFICAZIONE UMBRA
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- PSC REGIONE UMBRIA
- Policy Area
- Ambiente e risorse naturali
- Sector of intervention
- Rischi e adattamento climatico
Other projects in territory
Same theme
RICERCA E CONTENIMENTO DELLE PERDITE NELLA RETE ACQUEDOTTISTICA NEI TERRITORI DEL SUB-AMBITO 1 E 2 | € 6,400,000 |
PROGETTO CLE-COMUNE DI CANNARA | € 1,500 |