CUP: C61B03000140004
SECONDA TANGENZIALE OVEST DI PRATO LOTTO IVA.
SUMMARY OF THE PROJECT
SECONDA TANGENZIALE OVEST DI PRATO LOTTO IVA.
Implementation indicator
Estensione in lunghezza
- Target
- 3 km
- Achieved
- 3 km
Download project
Funding monitored
€ 7,310,584.17
of which cohesion funds
€ 7,110,584.17
Given name | Amount |
---|---|
Development and Cohesion Fund | 7110584.17 |
Municipality | 200000.00 |
Payments monitored
€ 7,310,584.15
of which cohesion funds
€ 7,110,584.15
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2006 | 570000.00 | 570000.00 | 7 |
2007 | 1808047.20 | 2378047.20 | 32 |
2008 | 1796515.12 | 4174562.32 | 57 |
2009 | 2012113.47 | 6186675.79 | 84 |
2010 | 386587.47 | 6573263.26 | 89 |
2011 | 537320.89 | 7110584.15 | 97 |
2012 | 0 | 7110584.15 | 97 |
2013 | 0 | 7110584.15 | 97 |
2014 | 0 | 7110584.15 | 97 |
2015 | 0 | 7110584.15 | 97 |
2016 | 200000.00 | 7310584.15 | 99 |
State of progress
Completed
Expected start: 01/04/2007
Effective start: 01/04/2007
Expected end: 31/12/2016
Effective end: 31/12/2016
Entities
- Planning body
- REGIONE TOSCANA
- Implementing body
- COMUNE DI PRATO
- Beneficiary
- REGIONE TOSCANA
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- PSC REGIONE TOSCANA
- Policy Area
- Trasporti e Mobilita'
- Sector of intervention
- Trasporto stradale