CUP: F84E00000000011
Adeguamento SRT74 'Maremmana' - Progetto di ampliamento e ammodernamento - I Lotto
SUMMARY OF THE PROJECT
Adeguamento SRT74 'Maremmana' - Progetto di ampliamento e ammodernamento - I Lotto
Implementation indicator
Estensione in lunghezza
- Target
- 1.50 km
- Achieved
- 1.50 km
Download project
Funding monitored
€ 4,113,684.89
of which cohesion funds
€ 4,113,684.89
Given name | Amount |
---|---|
Development and Cohesion Fund | 4113684.89 |
Payments monitored
€ 4,113,684.89
of which cohesion funds
€ 4,113,684.89
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2005 | 428584.36 | 428584.36 | 10 |
2006 | 1501096.88 | 1929681.24 | 46 |
2007 | 202718.76 | 2132400.00 | 51 |
2008 | 1229526.54 | 3361926.54 | 81 |
2009 | 0 | 3361926.54 | 81 |
2010 | 0 | 3361926.54 | 81 |
2011 | 751758.35 | 4113684.89 | 100 |
State of progress
Completed
Expected start: 26/01/2005
Effective start: 26/01/2005
Expected end: 13/03/2008
Effective end: 13/03/2008
Entities
- Planning body
- REGIONE TOSCANA
- Implementing body
- AMMINISTRAZIONE PROVINCIALE DI GROSSETO
- Beneficiary
- REGIONE TOSCANA
Programming area
- Programme
- PSC REGIONE TOSCANA
- Fondo Aree Sottoutilizzate 2000-2006
- 2000-2006 Underutilized Areas Fund
- Cohesion funds
- € 4,113,684.89
- Payments on cohesion funds
- € 4,113,684.89
- Policy Area
- Trasporti e Mobilita'
- Sector of intervention
- Trasporto stradale
Other projects in territory
Same theme
Same type of investment
S.R.T. 74 'Maremmana' - Progetto di ampliamento e ammodernamento- Lotto III | € 5,325,065 |
Adeguamento SRT74 'Maremmana' - Progetto di ampliamento e ammodernamento - II Lotto. | € 3,672,160 |