CUP: F23J02000030008
COLLETTORE FOGNARIO DA PIAN DELLE MACINAIE
SUMMARY OF THE PROJECT
COLLETTORE FOGNARIO DA PIAN DELLE MACINAIE
Implementation indicator
Ampliamento lunghezza rete
- Target
- 3,800 m
- Achieved
- 3,800 m
Download project
Funding monitored
€ 323,347.05
of which cohesion funds
€ 323,347.05
Given name | Amount |
---|---|
Development and Cohesion Fund | 323347.05 |
- Other resources - Private:
- € 426,653
Payments monitored
€ 320,773.05
of which cohesion funds
€ 320,773.05
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2008 | 115483.00 | 115483.00 | 35 |
2009 | 116919.00 | 232402.00 | 71 |
2010 | 0 | 232402.00 | 71 |
2011 | 0 | 232402.00 | 71 |
2012 | 0 | 232402.00 | 71 |
2013 | 0 | 232402.00 | 71 |
2014 | 3940.00 | 236342.00 | 73 |
2015 | 0 | 236342.00 | 73 |
2016 | 0 | 236342.00 | 73 |
2017 | 0 | 236342.00 | 73 |
2018 | 0 | 236342.00 | 73 |
2019 | 0 | 236342.00 | 73 |
2020 | 0 | 236342.00 | 73 |
2021 | 0 | 236342.00 | 73 |
2022 | 84431.05 | 320773.05 | 99 |
State of progress
Settled
Expected start: 01/04/2005
Effective start: 01/04/2005
Expected end: 30/09/2023
Effective end: not available
Entities
- Planning body
- REGIONE TOSCANA
- Implementing body
-
PROVVEDITORATO REGIONALE OO.PP
ACQUEDOTTO DEL FIORA SPA - Beneficiary
-
PROVVEDITORATO REGIONALE OO.PP
ACQUEDOTTO DEL FIORA SPA
Programming area
- Programme
- PSC REGIONE TOSCANA
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Cohesion funds
- € 323,347.05
- Payments on cohesion funds
- € 320,773.05
- Policy Area
- Ambiente e risorse naturali
- Sector of intervention
- Risorse idriche
Other projects in territory
Same theme
INFRASCI AM-01 / IMPIANTO DI APPROVVIGIONAMENTO IDRICO DELLA PARTE ALTA DEL MONTE AMIATA A SCOPO INNEVAMENTO PROGRAMMATO | € 2,070,323 |
DEPURAZIONE ABBADIA S. SALVATORE | € 1,750,487 |