CUP: H71F05000000006
Realizzazione Nuovo Centro Giovani di Piombino.
SUMMARY OF THE PROJECT
Realizzazione Nuovo Centro Giovani di Piombino.
Implementation indicator
Superficie oggetto di intervento
- Target
- 800 mq
- Achieved
- 800 mq
Download project
Funding monitored
€ 749,790.29
of which cohesion funds
€ 699,832.23
Given name | Amount |
---|---|
Development and Cohesion Fund | 699832.23 |
Municipality | 49958.06 |
Payments monitored
€ 749,790.28
of which cohesion funds
€ 699,832.22
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2003 | 3160.88 | 3160.88 | 0 |
2004 | 0 | 3160.88 | 0 |
2005 | 14022.53 | 17183.41 | 2 |
2006 | 585742.04 | 602925.45 | 80 |
2007 | 146168.83 | 749094.28 | 99 |
2008 | 696.00 | 749790.28 | 99 |
State of progress
Completed
Expected start: 27/09/2005
Effective start: 27/09/2005
Expected end: 28/09/2006
Effective end: 28/09/2006
Entities
- Planning body
- COMUNE DI PIOMBINO
- Implementing body
- COMUNE DI PIOMBINO
- Beneficiary
- REGIONE TOSCANA
Programming area
- Programme
- PSC REGIONE TOSCANA
- Fondo Aree Sottoutilizzate 2000-2006
- 2000-2006 Underutilized Areas Fund
- Cohesion funds
- € 699,832.23
- Payments on cohesion funds
- € 699,832.22
- Policy Area
- Istruzione e Formazione
- Sector of intervention
- Strutture educative e formative
Other projects in territory
Same theme
Same type of investment
Rifacimento del manto di copertura della parte est della Scuola Secondaria Statale Di I Grado Andrea Guardi Sezione di Via Togliatti | € 130,000 |