CUP: H91E17000330002
TERTENIA - COMPLETAMENTO LAVORI PER L'EFFICIENTAMENTO ED ADEGUAMENTO NORMATIVO DELL'IMPIANTO SPORTIVO SOVRACOMUNALE 'IS ARRANAS' - SERVIZI IGIENICI
SUMMARY OF THE PROJECT
TERTENIA - COMPLETAMENTO LAVORI PER L'EFFICIENTAMENTO ED ADEGUAMENTO NORMATIVO DELL'IMPIANTO SPORTIVO SOVRACOMUNALE 'IS ARRANAS' - SERVIZI IGIENICI
Implementation indicator
Superficie oggetto di intervento
- Target
- 1,000 mq
- Achieved
- 1,000 mq
Funding monitored
€ 27,129.56
of which cohesion funds
€ 27,129.56
Given name | Amount |
---|---|
Development and Cohesion Fund | 27129.56 |
- Economies:
- € 16,550.44
Payments monitored
€ 27,129.56
of which cohesion funds
€ 27,129.56
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2018 | 27129.56 | 27129.56 | 100 |
State of progress
Completed
Expected start: 30/01/2018
Effective start: 31/01/2018
Expected end: 30/05/2018
Effective end: 04/06/2018
Entities
- Planning body
- REGIONE AUTONOMA DELLA SARDEGNA
- Implementing body
-
REGIONE AUTONOMA DELLA SARDEGNA
COMUNE DI TERTENIA - Beneficiary
-
REGIONE AUTONOMA DELLA SARDEGNA
COMUNE DI TERTENIA
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- PSC REGIONE SARDEGNA
- Policy Area
- Riqualificazione urbana
- Sector of intervention
- Edilizia e spazi pubblici