CUP: D94E04000000002
ADEGUAMENTO STRUTTURE DEPURATIVE AI LIMITI DEL D. LGS 152/99. PROGETTO ESECUTIVO DEI COLLETTORI FOGNARI E DELLE STAZIONI DI SOLLEVAMENTO.
SUMMARY OF THE PROJECT
ADEGUAMENTO STRUTTURE DEPURATIVE AI LIMITI DEL D. LGS 152/99. PROGETTO ESECUTIVO DEI COLLETTORI FOGNARI E DELLE STAZIONI DI SOLLEVAMENTO.
Implementation indicator
Portata media equivalente
- Target
- 0.29 mc/s
- Achieved
- 0.41 mc/s
Funding monitored
€ 6,976,598.11
of which cohesion funds
€ 6,976,598.11
Given name | Amount |
---|---|
Development and Cohesion Fund | 6976598.11 |
Payments monitored
€ 6,976,598.11
of which cohesion funds
€ 6,976,598.11
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2004 | 1524464.75 | 1524464.75 | 21 |
2005 | 2362568.75 | 3887033.50 | 55 |
2006 | 1792854.25 | 5679887.75 | 81 |
2007 | 1040374.42 | 6720262.17 | 96 |
2008 | 14178.64 | 6734440.81 | 96 |
2009 | 143332.40 | 6877773.21 | 98 |
2010 | 98824.90 | 6976598.11 | 100 |
State of progress
Completed
Expected start: 20/04/2004
Effective start: 20/04/2004
Expected end: 20/10/2006
Effective end: 20/10/2006
Entities
- Planning body
- COMUNE DI CASTIADAS
- Implementing body
- COMUNE DI CASTIADAS
- Beneficiary
- REGIONE AUTONOMA DELLA SARDEGNA
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- PSC REGIONE SARDEGNA
- Policy Area
- Ambiente e risorse naturali
- Sector of intervention
- Risorse idriche