CUP: F21B96000000001
LAVORI DI AMMODERNAMENTO ED ADEGUAMENTO AL TIPO 1/B DELLE NORME C.N.R. 80, TRONCO 1A- TRATTO 2A - LOTTO1: DAL KM 22+400 AL KM 23+000. SVINCOLO DI BATTIPAGLIA INCLUSO E ASTA DI RACCORDO SS 18.
SUMMARY OF THE PROJECT
LAVORI DI AMMODERNAMENTO ED ADEGUAMENTO AL TIPO 1/B DELLE NORME C.N.R. 80, TRONCO 1A- TRATTO 2A - LOTTO1: DAL KM 22+400 AL KM 23+000. SVINCOLO DI BATTIPAGLIA INCLUSO E ASTA DI RACCORDO SS 18.
Implementation indicator
Estensione in lunghezza
- Target
- 0.60 km
- Achieved
- 0.60 km
Download project
Funding monitored
€ 39,252,539.15
of which cohesion funds
€ 3,861,207.09
Given name | Amount |
---|---|
Development and Cohesion Fund | 3861207.09 |
Another public source | 35391332.06 |
Payments monitored
€ 32,538,887.02
of which cohesion funds
€ 3,200,796.24
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2008 | 26321.98 | 26321.98 | 0 |
2009 | 0 | 26321.98 | 0 |
2010 | 12840679.12 | 12867001.10 | 32 |
2011 | 8981435.43 | 21848436.53 | 55 |
2012 | 6190070.32 | 28038506.85 | 71 |
2013 | 2913949.05 | 30952455.90 | 78 |
2014 | 1245115.94 | 32197571.84 | 82 |
2015 | 226445.19 | 32424017.03 | 82 |
2016 | 82061.38 | 32506078.41 | 82 |
2017 | 32808.61 | 32538887.02 | 82 |
State of progress
Open
Expected start: 18/11/2009
Effective start: 18/11/2009
Expected end: 03/07/2012
Effective end: 03/07/2012
Entities
- Planning body
- ANAS SOCIETA PER AZIONI
- Implementing body
- ANAS SOCIETA PER AZIONI
- Beneficiary
- ANAS SOCIETA PER AZIONI
Programming area
- Programme
- PSC CAMPANIA
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Cohesion funds
- € 3,861,207.09
- Payments on cohesion funds
- € 3,200,796.24
- Policy Area
- Trasporti e Mobilita'
- Sector of intervention
- Trasporto stradale