This project is eliminated from views and totals because it will be deactivated due to migration in the Development and Cohesion Plan.
Updated on 31/10/2024
Funding monitored € 3,800,000.00 of which cohesion funds € 3,800,000.00
Given name Amount
Development and Cohesion Fund3800000.00
Payments monitored € 1,046,957.82 of which cohesion funds € 1,046,957.82
Year Amount Cumulative amount Percentage on public financing
20177737.247737.240
20183823.1711560.410
201952762.3664322.771
202016689.9981012.762
2021941009.351022022.1126
202224935.711046957.8227

State of progress

Open
Expected start: 27/01/2021
Effective start: 27/01/2021
Expected end: 28/10/2024
Effective end: not available

Type

Theme

Territory

Entities

Planning body
REGIONE AUTONOMA DELLA SARDEGNA
Implementing body
CONSORZIO INDUSTRIALE PROVINCIALE MEDIO CAMPIDANO VILLACIDRO
Beneficiary
CONSORZIO INDUSTRIALE PROVINCIALE MEDIO CAMPIDANO VILLACIDRO
Priority QSN
Energia e ambiente: uso sostenibile e efficiente delle risorse per lo sviluppo
General objective QSN
Garantire le condizioni di sostenibilità ambientale dello sviluppo e livelli adeguati di servizi ambientali per la popolazione e le imprese
Specific objective QSN
Accrescere la capacità di offerta, la qualità e l'efficienza del servizio idrico, e rafforzare la difesa del suolo e la prevenzione dei rischi naturali

Programming area

Programme
PROGRAMMA OBIETTIVI DI SERVIZIO REGIONE SARDEGNA
2007-2013 National Development and Cohesion Fund
2007-2013 National Development and Cohesion Fund
Cohesion funds
€ 3,800,000.00
Payments on cohesion funds
€ 1,046,957.82
Line
Servizio idrico integrato
Action
Interventi nel settore depurativo-fognario