CUP: F77H02000370001
S.S. 96 'BARESE' - TRONCO GRAVINA - BARI.LAVORI PER L'AMMODERNAMENTO E ADEGUAMENTO ALLA SEZ. CNR DEL TRATTO COMPRESO FRA LA FINE DELLA VARIANTE DI ALTAMURA E L'INIZIO DELLA VARIANTE DI TORITTO - 1A STRALCIO DAL KM 93+598 AL KM 99+040
SUMMARY OF THE PROJECT
S.S. 96 'BARESE' - TRONCO GRAVINA - BARI.LAVORI PER L'AMMODERNAMENTO E ADEGUAMENTO ALLA SEZ. CNR DEL TRATTO COMPRESO FRA LA FINE DELLA VARIANTE DI ALTAMURA E L'INIZIO DELLA VARIANTE DI TORITTO - 1A STRALCIO DAL KM 93+598 AL KM 99+040
Implementation indicator
Non richesto (Migrazione PSC)
- Target
- 0.01 num
- Achieved
- 0.01 num
Funding monitored
€ 37,376,715.34
of which cohesion funds
€ 37,376,715.34
Given name | Amount |
---|---|
Development and Cohesion Fund | 37376715.34 |
Payments monitored
€ 0.00
of which cohesion funds
€ 0.00
Year | Amount | Cumulative amount | Percentage on public financing |
---|
State of progress
Not started
Expected start: 11/01/2010
Effective start: 01/03/2010
Expected end: 31/12/2015
Effective end: 13/10/2014
Entities
- Planning body
- REGIONE PUGLIA
- Implementing body
- ANAS SOCIETA PER AZIONI
- Beneficiary
- REGIONE PUGLIA
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- PSC REGIONE PUGLIA
- Policy Area
- Trasporti e Mobilita'
- Sector of intervention
- Trasporto stradale