Riqualificazione degli attraversamenti ferroviari e della viabilit urbana marginale
SUMMARY OF THE PROJECT
Riqualificazione degli attraversamenti ferroviari e della viabilit urbana marginale
Implementation indicator
Non richesto (Migrazione PSC)
- Target
- 0.01 num
- Achieved
- 0.01 num
Download project
Funding monitored
€ 4,000,600.84
of which cohesion funds
€ 4,000,600.84
Given name | Amount |
---|---|
Development and Cohesion Fund | 4000600.84 |
- Economies:
- € 34,791.13
Payments monitored
€ 4,000,600.84
of which cohesion funds
€ 4,000,600.84
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2014 | 79819.09 | 79819.09 | 1 |
2015 | 411999.69 | 491818.78 | 12 |
2016 | 3185736.60 | 3677555.38 | 91 |
2017 | 0 | 3677555.38 | 91 |
2018 | 0 | 3677555.38 | 91 |
2019 | 323045.46 | 4000600.84 | 100 |
State of progress
Completed
Expected start: 17/03/2014
Effective start: 17/03/2014
Expected end: 13/10/2014
Effective end: 19/12/2015
Entities
- Planning body
- REGIONE PUGLIA
- Implementing body
- COMUNE DI GIOIA DEL COLLE
- Beneficiary
- REGIONE PUGLIA
Programming area
- Programme
- PSC REGIONE PUGLIA
- Fondo Aree Sottoutilizzate 2000-2006
- 2000-2006 Underutilized Areas Fund
- Cohesion funds
- € 4,000,600.84
- Payments on cohesion funds
- € 4,000,600.84
- Policy Area
- Trasporti e Mobilita'
- Sector of intervention
- Trasporto stradale