CUP: E44H07000290001
Completamento opere di urbanizzazione primaria all'interno della zona industriale
SUMMARY OF THE PROJECT
Completamento opere di urbanizzazione primaria all'interno della zona industriale
Implementation indicator
Non richesto (Migrazione PSC)
- Target
- 0.01 num
- Achieved
- 0.01 num
Download project
Funding monitored
€ 1,420,000.00
of which cohesion funds
€ 1,220,000.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 1220000.00 |
Municipality | 200000.00 |
Payments monitored
€ 1,395,866.71
of which cohesion funds
€ 1,199,265.77
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2008 | 27580.80 | 27580.80 | 1 |
2009 | 359376.80 | 386957.60 | 27 |
2010 | 866593.86 | 1253551.46 | 88 |
2011 | 142315.25 | 1395866.71 | 98 |
State of progress
Completed
Expected start: 04/08/2009
Effective start: 04/08/2009
Expected end: 19/08/2010
Effective end: 19/08/2010
Entities
- Planning body
- COMUNE DI SAN PANCRAZIO SALENTINO
- Implementing body
- COMUNE DI SAN PANCRAZIO SALENTINO
- Beneficiary
- REGIONE PUGLIA
Programming area
- Programme
- PSC REGIONE PUGLIA
- Fondo Aree Sottoutilizzate 2000-2006
- 2000-2006 Underutilized Areas Fund
- Cohesion funds
- € 1,220,000.00
- Payments on cohesion funds
- € 1,199,265.77
- Policy Area
- Competitivita' Imprese
- Sector of intervention
- Industria e servizi