CUP: E98E05000010001
INTERVENTI DI RIQUALIFICAZIONE DEL QUARTIERE FIERISTICO E COSTRUZIONE DI UN NUOVO PADIGLIONE ESPOSITIVO
SUMMARY OF THE PROJECT
INTERVENTI DI RIQUALIFICAZIONE DEL QUARTIERE FIERISTICO E COSTRUZIONE DI UN NUOVO PADIGLIONE ESPOSITIVO
Download project
Funding monitored
€ 27,950,030.00
of which cohesion funds
€ 27,950,030.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 25000000.00 |
Another public source | 2950030.00 |
Payments monitored
€ 27,950,030.00
of which cohesion funds
€ 27,950,030.00
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2006 | 105120.88 | 105120.88 | 0 |
2007 | 0 | 105120.88 | 0 |
2008 | 3644879.12 | 3750000.00 | 13 |
2009 | 10878989.78 | 14628989.78 | 52 |
2010 | 7807563.72 | 22436553.50 | 80 |
2011 | 4624447.22 | 27061000.72 | 96 |
2012 | 889029.28 | 27950030.00 | 100 |
State of progress
Completed
Expected start: 17/01/2008
Effective start: 17/01/2008
Expected end: 05/10/2011
Effective end: 05/10/2011
Entities
- Planning body
- ENTE AUTONOMO FIERA DEL LEVANTE
- Implementing body
- ENTE AUTONOMO FIERA DEL LEVANTE
- Beneficiary
- REGIONE PUGLIA
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- PSC REGIONE PUGLIA
- Policy Area
- Competitivita' Imprese
- Sector of intervention
- Industria e servizi