CUP: E94H06000110001
Lavori di adeguamento e completamento della rete fognaria comunale.
SUMMARY OF THE PROJECT
Lavori di adeguamento e completamento della rete fognaria comunale.
Implementation indicator
Non richesto (Migrazione PSC)
- Target
- 0.01 num
- Achieved
- 0.01 num
Download project
Funding monitored
€ 720,000.00
of which cohesion funds
€ 720,000.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 720000.00 |
Payments monitored
€ 719,985.13
of which cohesion funds
€ 719,985.13
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2011 | 420425.63 | 420425.63 | 58 |
2012 | 299559.50 | 719985.13 | 99 |
State of progress
Completed
Expected start: 25/03/2009
Effective start: 25/03/2009
Expected end: 23/06/2010
Effective end: 23/06/2010
Entities
- Planning body
- REGIONE PUGLIA
- Implementing body
- COMUNE DI VOLTURINO
- Beneficiary
- REGIONE PUGLIA
Programming area
- Programme
- PSC REGIONE PUGLIA
- Fondo Aree Sottoutilizzate 2000-2006
- 2000-2006 Underutilized Areas Fund
- Cohesion funds
- € 720,000.00
- Payments on cohesion funds
- € 719,985.13
- Policy Area
- Ambiente e risorse naturali
- Sector of intervention
- Risorse idriche