CUP: E56E09000120006
Martignano - Realizzazione do Sistemi di collettamento differenziati per le acque piovane ed adeguamento scarichi finali
SUMMARY OF THE PROJECT
Martignano - Realizzazione do Sistemi di collettamento differenziati per le acque piovane ed adeguamento scarichi finali
Implementation indicator
Non richesto (Migrazione PSC)
- Target
- 0.01 num
- Achieved
- 0.01 num
Download project
Funding monitored
€ 375,000.00
of which cohesion funds
€ 348,750.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 348750.00 |
Municipality | 26250.00 |
Payments monitored
€ 350,172.36
of which cohesion funds
€ 325,660.28
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2009 | 150.00 | 150.00 | 0 |
2010 | 243414.59 | 243564.59 | 64 |
2011 | 106607.77 | 350172.36 | 93 |
State of progress
Open
Expected start: 07/12/2009
Effective start: 07/12/2009
Expected end: 26/02/2010
Effective end: 26/02/2010
Entities
- Planning body
- REGIONE PUGLIA
- Implementing body
- COMUNE DI MARTIGNANO
- Beneficiary
- REGIONE PUGLIA
Programming area
- Programme
- PSC REGIONE PUGLIA
- Fondo Aree Sottoutilizzate 2000-2006
- 2000-2006 Underutilized Areas Fund
- Cohesion funds
- € 348,750.00
- Payments on cohesion funds
- € 325,660.28
- Policy Area
- Ambiente e risorse naturali
- Sector of intervention
- Risorse idriche