CUP: F63J04000090006
VICO DEL GARGANO - REALIZZAZIONE DO SISTEMI DI COLLETTAMENTO DIFFERENZIATI PER LE ACQUE PIOVANE ED ADEGUAMENTO SCARICHI FINALI
SUMMARY OF THE PROJECT
VICO DEL GARGANO - REALIZZAZIONE DO SISTEMI DI COLLETTAMENTO DIFFERENZIATI PER LE ACQUE PIOVANE ED ADEGUAMENTO SCARICHI FINALI
Download project
Funding monitored
€ 387,342.68
of which cohesion funds
€ 359,841.35
Given name | Amount |
---|---|
Development and Cohesion Fund | 359841.35 |
Municipality | 27501.33 |
Payments monitored
€ 287,164.29
of which cohesion funds
€ 266,775.61
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2009 | 1591.10 | 1591.10 | 0 |
2010 | 201089.87 | 202680.97 | 52 |
2011 | 84483.32 | 287164.29 | 74 |
State of progress
Open
Expected start: 30/12/2009
Effective start: 30/12/2009
Expected end: 22/03/2011
Effective end: 22/03/2011
Entities
- Planning body
- REGIONE PUGLIA
- Implementing body
- COMUNE DI VICO DEL GARGANO
- Beneficiary
- REGIONE PUGLIA
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- PSC REGIONE PUGLIA
- Policy Area
- Ambiente e risorse naturali
- Sector of intervention
- Risorse idriche