CUP: C73B09000130006
Guagnano - Realizzazione do Sistemi di collettamento differenziati per le acque piovane ed adeguamento scarichi finali
SUMMARY OF THE PROJECT
Guagnano - Realizzazione do Sistemi di collettamento differenziati per le acque piovane ed adeguamento scarichi finali
Implementation indicator
Destinatari
- Target
- 1 num
- Achieved
- 1 num
Download project
Funding monitored
€ 1,625,265.99
of which cohesion funds
€ 1,511,497.37
Given name | Amount |
---|---|
Development and Cohesion Fund | 1511497.37 |
Municipality | 113768.62 |
- Economies:
- € 6,981.38
Payments monitored
€ 865,160.00
of which cohesion funds
€ 804,598.80
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2009 | 682.54 | 682.54 | 0 |
2010 | 48444.62 | 49127.16 | 3 |
2011 | 816032.84 | 865160.00 | 53 |
State of progress
Open
Expected start: 28/07/2010
Effective start: 28/07/2010
Expected end: 31/12/2013
Effective end: not available
Entities
- Planning body
- REGIONE PUGLIA
- Implementing body
- COMUNE DI GUAGNANO
- Beneficiary
- REGIONE PUGLIA
Programming area
- Programme
- PSC REGIONE PUGLIA
- Fondo Aree Sottoutilizzate 2000-2006
- 2000-2006 Underutilized Areas Fund
- Cohesion funds
- € 1,511,497.37
- Payments on cohesion funds
- € 804,598.80
- Policy Area
- Ambiente e risorse naturali
- Sector of intervention
- Risorse idriche