CUP: E91E04000080001
SISTEMA INTEGRATO COSTITUITO DA LINEE DI SELEZIONE, BIOSTABILIZZAZIONE DEI RIFIUTI URBANI E DISCARICHE DI SERVIZIO/SOCCORSO
SUMMARY OF THE PROJECT
SISTEMA INTEGRATO COSTITUITO DA LINEE DI SELEZIONE, BIOSTABILIZZAZIONE DEI RIFIUTI URBANI E DISCARICHE DI SERVIZIO/SOCCORSO
Implementation indicator
Non richesto (Migrazione PSC)
- Target
- 0.01 num
- Achieved
- 0.01 num
Download project
Funding monitored
€ 19,478,990.00
of which cohesion funds
€ 18,900,000.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 5000000.00 |
Another public source | 14478990.00 |
Payments monitored
€ 1,750,000.00
of which cohesion funds
€ 1,750,000.00
8%
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2011 | 1750000.00 | 1750000.00 | 8 |
State of progress
Open
Expected start: 20/04/2009
Effective start: 20/04/2009
Expected end: 22/03/2010
Effective end: 22/03/2010
Entities
- Planning body
- Soprintendenza Archeologica per l'Abruzzo
- Implementing body
- Soprintendenza Archeologica per l'Abruzzo
- Beneficiary
- REGIONE PUGLIA
Programming area
- Programme
- PSC REGIONE PUGLIA
- Fondo Aree Sottoutilizzate 2000-2006
- 2000-2006 Underutilized Areas Fund
- Cohesion funds
- € 18,900,000.00
- Payments on cohesion funds
- € 1,750,000.00
- Policy Area
- Ambiente e risorse naturali
- Sector of intervention
- Natura e biodiversita'