CUP: B48G06000050006
Ripristino e riproposizione idraulica del fiume Lato monte- valle- attraversamento SS 106
SUMMARY OF THE PROJECT
Ripristino e riproposizione idraulica del fiume Lato monte- valle- attraversamento SS 106
Implementation indicator
Non richesto (Migrazione PSC)
- Target
- 0.01 num
- Achieved
- 0.01 num
Download project
Funding monitored
€ 7,890,070.44
of which cohesion funds
€ 7,890,070.44
Given name | Amount |
---|---|
Development and Cohesion Fund | 7890070.44 |
Payments monitored
€ 7,653,368.33
of which cohesion funds
€ 7,653,368.33
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2006 | 386147.55 | 386147.55 | 4 |
2007 | 1922791.42 | 2308938.97 | 29 |
2008 | 2012875.47 | 4321814.44 | 54 |
2009 | 1035670.51 | 5357484.95 | 67 |
2010 | 483692.35 | 5841177.30 | 74 |
2011 | 1812191.03 | 7653368.33 | 97 |
State of progress
Completed
Expected start: 12/06/2006
Effective start: 12/06/2006
Expected end: 31/12/2015
Effective end: 31/12/2015
Entities
- Planning body
- REGIONE PUGLIA
- Implementing body
- COMUNE DI CASTELLANETA
- Beneficiary
- REGIONE PUGLIA
Programming area
- Programme
- PSC REGIONE PUGLIA
- Fondo Aree Sottoutilizzate 2000-2006
- 2000-2006 Underutilized Areas Fund
- Cohesion funds
- € 7,890,070.44
- Payments on cohesion funds
- € 7,653,368.33
- Policy Area
- Ambiente e risorse naturali
- Sector of intervention
- Risorse idriche