CUP: G91I19000010003
Elettrificazione della tratta ferroviaria Adria Mestre fra le stazioni di Adria e Mira Buse
SUMMARY OF THE PROJECT
Elettrificazione della tratta ferroviaria Adria Mestre fra le stazioni di Adria e Mira Buse
Implementation indicator
Lunghezza totale delle linee ferroviarie ricostruite o rinnovate
- Target
- 48 km
- Achieved
- 0 km
Download project
Funding monitored
€ 40,750,000.00
of which cohesion funds
€ 11,250,000.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 11250000.00 |
Region | 7500000.00 |
Another public source | 22000000.00 |
Payments monitored
€ 23,778,895.78
of which cohesion funds
€ 6,565,554.08
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2020 | 3000.00 | 3000.00 | 0 |
2021 | 1428644.47 | 1431644.47 | 3 |
2022 | 242193.68 | 1673838.15 | 4 |
2023 | 1951647.31 | 3625485.46 | 8 |
2024 | 18029289.23 | 21654774.69 | 53 |
2025 | 2124121.09 | 23778895.78 | 58 |
State of progress
Open
Expected start: 14/02/2023
Effective start: 14/02/2023
Expected end: 28/05/2025
Effective end: not available
Entities
- Planning body
- REGIONE DEL VENETO
- Implementing body
- REGIONE DEL VENETO
- Beneficiary
- Infrastrutture Venete Srl
Programming area
- Programme
- ACCORDO COESIONE VENETO - FSC ANTICIPAZIONI
- 2021-2027 National Development and Cohesion Fund
- 2021-2027 National Development and Cohesion Fund
- Cohesion funds
- € 11,250,000.00
- Payments on cohesion funds
- € 6,565,554.08
- Policy Area
- Trasporti e Mobilita'
- Sector of intervention
- Trasporto ferroviario