CUP: G91I19000010003
ELETTRIFICAZIONE DELLA TRATTA FERROVIARIA ADRIA MESTRE FRA LE STAZIONI DI ADRIA E MIRA BUSE
SUMMARY OF THE PROJECT
ELETTRIFICAZIONE DELLA TRATTA FERROVIARIA ADRIA MESTRE FRA LE STAZIONI DI ADRIA E MIRA BUSE
Implementation indicator
Lunghezza totale delle linee ferroviarie ricostruite o rinnovate
- Target
- 48 km
- Achieved
- 0 km
Download project
Funding monitored
€ 40,750,000.00
of which cohesion funds
€ 11,250,000.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 11250000.00 |
Region | 7500000.00 |
Another public source | 22000000.00 |
Payments monitored
€ 1,524,720.25
of which cohesion funds
€ 420,935.06
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2020 | 3000.00 | 3000.00 | 0 |
2021 | 1428644.47 | 1431644.47 | 3 |
2022 | 93075.78 | 1524720.25 | 3 |
State of progress
Open
Expected start: 14/02/2023
Effective start: 14/02/2023
Expected end: 28/03/2025
Effective end: not available
Entities
- Planning body
- REGIONE DEL VENETO
- Implementing body
- REGIONE DEL VENETO
- Beneficiary
- INFRASTRUTTURE VENETE SRL
Programming area
- Programme
- FSC ANTICIPAZIONI VENETO 2021-2027
- 2021-2027 National Development and Cohesion Fund
- 2021-2027 National Development and Cohesion Fund
- Cohesion funds
- € 11,250,000.00
- Payments on cohesion funds
- € 420,935.06
- Policy Area
- Trasporti e Mobilita'
- Sector of intervention
- Trasporto ferroviario