CUP: F21B19000360002
COMPLETAMENTO DELLA MESSA IN SICUREZZA DELLA STRADA DI COLLEGAMENTO DEI COMUNI DI LIMOSANO CASTROPIGNANO SANTANGELO LIMOSANO E FOSSALTO - COMUNE DI LIMOSANO
SUMMARY OF THE PROJECT
COMPLETAMENTO DELLA MESSA IN SICUREZZA DELLA STRADA DI COLLEGAMENTO DEI COMUNI DI LIMOSANO CASTROPIGNANO SANTANGELO LIMOSANO E FOSSALTO
Implementation indicator
Lunghezza totale delle strade ricostruite o rinnovate
- Target
- 2 km
- Achieved
- 0.20 km
Download project
Funding monitored
€ 1,600,000.00
of which cohesion funds
€ 1,600,000.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 1600000.00 |
Payments monitored
€ 427,354.31
of which cohesion funds
€ 427,354.31
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2024 | 160000.00 | 160000.00 | 10 |
2025 | 267354.31 | 427354.31 | 26 |
State of progress
Open
Expected start: 18/09/2023
Effective start: 18/09/2023
Expected end: 31/03/2025
Effective end: not available
Entities
- Planning body
- REGIONE MOLISE
- Implementing body
- COMUNE DI LIMOSANO
- Beneficiary
- COMUNE DI LIMOSANO
- Executor
- PAOLUCCI COSTRUZIONI S.R.L.
Programming area
- Programme
- ACCORDO COESIONE MOLISE - FSC ANTICIPAZIONI
- 2021-2027 National Development and Cohesion Fund
- 2021-2027 National Development and Cohesion Fund
- Cohesion funds
- € 1,600,000.00
- Payments on cohesion funds
- € 427,354.31
- Policy Area
- Trasporti e Mobilita'
- Sector of intervention
- Trasporto stradale