CUP: B34C12000150004
SCOLMATORE DEL TORRENTE BISAGNO 1 LOTTO TORRENTE FEREGGIANO 1 STRALCIO IN COMUNE DI GENOVA
SUMMARY OF THE PROJECT
SCOLMATORE DEL TORRENTE BISAGNO 1 LOTTO TORRENTE FEREGGIANO 1 STRALCIO IN COMUNE DI GENOVA
Implementation indicator
Estensione dell'intervento in lunghezza
- Target
- 3,500 m
- Achieved
- 3,500 m
Download project
Funding monitored
€ 45,000,000.00
of which cohesion funds
€ 5,000,000.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 5000000.00 |
Status: other measures | 25000000.00 |
Municipality | 15000000.00 |
Payments monitored
€ 40,758,745.90
of which cohesion funds
€ 4,528,745.75
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2014 | 406121.08 | 406121.08 | 0 |
2015 | 3810146.55 | 4216267.63 | 9 |
2016 | 1453012.48 | 5669280.11 | 12 |
2017 | 7157768.18 | 12827048.29 | 28 |
2018 | 9642397.64 | 22469445.93 | 49 |
2019 | 12776180.27 | 35245626.20 | 78 |
2020 | 4855601.30 | 40101227.50 | 89 |
2021 | 657518.40 | 40758745.90 | 90 |
State of progress
Open
Expected start: 07/04/2015
Effective start: 02/07/2015
Expected end: 30/09/2020
Effective end: 30/09/2020
Entities
- Planning body
- REGIONE LIGURIA
- Implementing body
- COMMISSARIO STRAORDINARIO DELEGATO PER INTERVENTI DI MITIGAZIONE RISCHIO IDROGEOLOGICO REGIONE LIGURIA
- Beneficiary
- COMUNE DI GENOVA
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- PSC MINISTERO DELL'AMBIENTE E DELLA SICUREZZA ENERGETICA
- Policy Area
- Ambiente e risorse naturali
- Sector of intervention
- Rischi e adattamento climatico