CUP: J94H20001270001
PROGETTO I.T.A.S.C. INNOVAZIONE, TURISMO, ACCESSIBILITA, SOSTENIBILITA, CULTURA
SUMMARY OF THE PROJECT
PROGETTO I.T.A.S.C. INNOVAZIONE, TURISMO, ACCESSIBILITA, SOSTENIBILITA, CULTURA*CENTRO STORICO E SENTIERO FRASSATI*PROGETTO I.T.A.S.C. INNOVAZIONE, TURISMO, ACCESSIBILITA, SOSTENIBILITA, CULTURA
Implementation indicator
Superficie oggetto di intervento
- Target
- 1,000 mq
- Achieved
- 0 mq
Download project
Funding monitored
€ 999,178.68
of which cohesion funds
€ 999,178.68
Given name | Amount |
---|---|
Revolving Fund | 999178.68 |
Payments monitored
€ 0.00
of which cohesion funds
€ 0.00
Year | Amount | Cumulative amount | Percentage on public financing |
---|
State of progress
Open
Expected start: 15/10/2023
Effective start: 26/03/2023
Expected end: 30/10/2026
Effective end: not available
Entities
- Planning body
- MINISTERO DELLA CULTURA
- Implementing body
- COMUNE DI ROSETO VALFORTORE
- Beneficiary
- COMUNE DI ROSETO VALFORTORE
Programming area
- Programme
- POC CULTURA
- None
- Piano d'Azione Coesione 2014/2020
- Cohesion funds
- € 999,178.68
- Payments on cohesion funds
- € 0.00