CUP: J93H10000000007
Realizzazione nuova condotta di adduzione da campo pozzi a serbatoio S. Carlo DN500
SUMMARY OF THE PROJECT
Realizzazione nuova condotta di adduzione da campo pozzi a serbatoio S. Carlo DN500
Implementation indicator
Non richesto (Migrazione PSC)
- Target
- 0.01 num
- Achieved
- 0.01 num
Download project
Funding monitored
€ 466,073.15
of which cohesion funds
€ 215,000.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 215000.00 |
Another public source | 251073.15 |
Payments monitored
€ 466,073.15
of which cohesion funds
€ 214,999.98
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2011 | 3016.00 | 3016.00 | 0 |
2012 | 0 | 3016.00 | 0 |
2013 | 36823.51 | 39839.51 | 8 |
2014 | 168790.07 | 208629.58 | 44 |
2015 | 99841.58 | 308471.16 | 66 |
2016 | 44725.40 | 353196.56 | 75 |
2017 | 0 | 353196.56 | 75 |
2018 | 107845.78 | 461042.34 | 98 |
2019 | 0 | 461042.34 | 98 |
2020 | 5030.81 | 466073.15 | 100 |
State of progress
Completed
Expected start: 13/09/2013
Effective start: 13/09/2013
Expected end: 04/02/2017
Effective end: 04/02/2017
Entities
- Planning body
- REGIONE PIEMONTE
- Implementing body
- REGIONE PIEMONTE
- Beneficiary
- Acquedotto della Piana S.p.A.
Programming area
- Programme
- PSC PIEDMONT
- Fondo Aree Sottoutilizzate 2000-2006
- 2000-2006 Underutilized Areas Fund
- Cohesion funds
- € 215,000.00
- Payments on cohesion funds
- € 214,999.98
- Policy Area
- Ambiente e risorse naturali
- Sector of intervention
- Risorse idriche