CUP: E72J08000050002
SISTEMAZIONE VERSANTE PIANA TONI - RIO VALPIANA - COMPLETAMENTO
SUMMARY OF THE PROJECT
SISTEMAZIONE VERSANTE PIANA TONI - RIO VALPIANA - COMPLETAMENTO
Implementation indicator
Superficie oggetto di intervento
- Target
- 3,000 mq
- Achieved
- 3,000 mq
Download project
Funding monitored
€ 185,728.97
of which cohesion funds
€ 185,728.97
Given name | Amount |
---|---|
Development and Cohesion Fund | 185728.97 |
Payments monitored
€ 185,728.97
of which cohesion funds
€ 185,728.97
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2008 | 21608.40 | 21608.40 | 11 |
2009 | 0 | 21608.40 | 11 |
2010 | 98577.27 | 120185.67 | 64 |
2011 | 65543.30 | 185728.97 | 100 |
State of progress
Completed
Expected start: 22/05/2009
Effective start: 22/05/2009
Expected end: 03/05/2010
Effective end: 03/05/2010
Entities
- Planning body
- REGIONE PIEMONTE
- Implementing body
- COMUNE DI MOLLIA
- Beneficiary
- REGIONE PIEMONTE
Programming area
- Programme
- PSC PIEDMONT
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Cohesion funds
- € 185,728.97
- Payments on cohesion funds
- € 185,728.97
- Policy Area
- Ambiente e risorse naturali
- Sector of intervention
- Rischi e adattamento climatico