CUP: E42B02000150001
Sistemazione frana frazione Torno
SUMMARY OF THE PROJECT
Sistemazione frana frazione Torno
Implementation indicator
Non richesto (Migrazione PSC)
- Target
- 0.01 num
- Achieved
- 0.01 num
Download project
Funding monitored
€ 215,939.73
of which cohesion funds
€ 215,939.73
Given name | Amount |
---|---|
Development and Cohesion Fund | 215939.73 |
Payments monitored
€ 215,939.73
of which cohesion funds
€ 215,939.73
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2004 | 22362.24 | 22362.24 | 10 |
2005 | 118582.64 | 140944.88 | 65 |
2006 | 74994.85 | 215939.73 | 100 |
State of progress
Completed
Expected start: 27/09/2004
Effective start: 27/09/2004
Expected end: 30/06/2005
Effective end: 30/06/2005
Entities
- Planning body
- REGIONE PIEMONTE
- Implementing body
- COMUNE DI FOBELLO
- Beneficiary
- COMUNE DI FOBELLO
Programming area
- Programme
- PSC PIEDMONT
- Fondo Aree Sottoutilizzate 2000-2006
- 2000-2006 Underutilized Areas Fund
- Cohesion funds
- € 215,939.73
- Payments on cohesion funds
- € 215,939.73
- Policy Area
- Ambiente e risorse naturali
- Sector of intervention
- Rischi e adattamento climatico
Other projects in territory
Same type of investment
banda Ultralarga nelle aree bianche del territorio della Regione Piemonte con FONDI FSC | € 53,745,935 |