CUP: E62B02000300001
Sistemazione idrulica del torrente Tatorba - secondo lotto
SUMMARY OF THE PROJECT
Sistemazione idrulica del torrente Tatorba - secondo lotto
Implementation indicator
Non richesto (Migrazione PSC)
- Target
- 0.01 num
- Achieved
- 0.01 num
Download project
Funding monitored
€ 229,191.02
of which cohesion funds
€ 229,191.02
Given name | Amount |
---|---|
Development and Cohesion Fund | 229191.02 |
Payments monitored
€ 229,191.02
of which cohesion funds
€ 229,191.02
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2004 | 7831.80 | 7831.80 | 3 |
2005 | 33853.43 | 41685.23 | 18 |
2006 | 126154.65 | 167839.88 | 73 |
2007 | 61351.14 | 229191.02 | 100 |
State of progress
Completed
Expected start: 06/12/2004
Effective start: 06/12/2004
Expected end: 30/06/2006
Effective end: 30/06/2006
Entities
- Planning body
- REGIONE PIEMONTE
- Implementing body
- COMUNITA' MONTANA LANGA ASTIGIANA - VAL BORMIDA
- Beneficiary
- COMUNITA' MONTANA LANGA ASTIGIANA - VAL BORMIDA
Programming area
- Programme
- PSC PIEDMONT
- Fondo Aree Sottoutilizzate 2000-2006
- 2000-2006 Underutilized Areas Fund
- Cohesion funds
- € 229,191.02
- Payments on cohesion funds
- € 229,191.02
- Policy Area
- Ambiente e risorse naturali
- Sector of intervention
- Rischi e adattamento climatico