CUP: D71E16000300001
SISTEMA TRAM PALERMO - FASE II
SUMMARY OF THE PROJECT
PROGETTO DI REALIZZAZIONE DI TRE TRATTE TRAMVIARIE
Implementation indicator
Lunghezza totale delle linee tranviarie e metropolitane nuove o migliorate
- Target
- 21.60 km
- Achieved
- 0 km
Funding monitored
€ 254,067,537.00
of which cohesion funds
€ 198,872,027.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 198872027.00 |
Region | 49533991.00 |
Municipality | 5661519.00 |
Payments monitored
€ 12,413,215.67
of which cohesion funds
€ 12,413,215.67
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2018 | 1235101.14 | 1235101.14 | 0 |
2019 | 10810343.95 | 12045445.09 | 4 |
2020 | 112000.00 | 12157445.09 | 4 |
2021 | 46176.00 | 12203621.09 | 4 |
2022 | 7800.00 | 12211421.09 | 4 |
2023 | 201794.58 | 12413215.67 | 4 |
State of progress
Open
Expected start: 01/08/2024
Effective start: not available
Expected end: 31/10/2027
Effective end: not available
Entities
- Planning body
- COMUNE DI PALERMO
- Implementing body
- COMUNE DI PALERMO
- Beneficiary
- COMUNE DI PALERMO
At the School of OpenCohesion
OpenCoesione goes to School followed this project in edition 2022-23 with the team “TRAM-BUSTO A PAGLIARELLI” of “ISTITUTO COMPRENSIVO GIUSEPPE SCELSA -PA PALERMO” of Palermo, PALERMO.
Read the Monithon report.
View the creative output.
Read the Monithon report.
View the creative output.
OpenCoesione goes to School followed this project in edition 2021-22 with the team “Tram-sformers” of “ISTITUTO SUPERIORE L.EINAUDI-PARETO PALERMO” of Palermo, PALERMO.
Read the Monithon report.
View the creative output.
Read the Monithon report.
View the creative output.
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- PSC CITTA' METROPOLITANA DI PALERMO
- Policy Area
- Trasporti e Mobilita'
- Sector of intervention
- Mobilita' urbana
Other projects in territory
Same theme
Same type of investment
SISTEMA TRAM CITTA' DI PALERMO | € 298,886,604 |
RADDOPPIO FERROVIARIO PALERMO - CARINI - TRATTA B - NOTABARTOLO - EMS/LA MALFA | € 290,894,000 |
REALIZZAZIONE DELLA CHIUSURA DELL'ANELLO FERROVIARIO DI PALERMO | € 152,095,271 |
COMPLETAMENTO COLLETTORE FOGNARIO DELLA ZONA SUD-EST DI PALERMO. (33414) | € 47,313,795 |
SCMT SOTTOSISTEMA TERRA SICILIA | € 47,194,288 |