CUP: F24I18000000009
CHIESA S. MARIA DI COSTANTINOPOLI TAVENNA CB)
SUMMARY OF THE PROJECT
LINTERVENTO RIGUARDA ESSENZIALMENTE LA RIMOZIONE DELLA STRUTTURA LIGNEA DI COPERTURA CON SOSTITUZIONE DI ELEMENTI NUOVI RELATIVAMENTE ALLE PARTI AMMALORATE, POSA IN OPERA E IMPERMEABILIZZAZIONE E COPPI, LATTONERIA, RIPRISTINO DELLE PARTI AMMALORATE DELLINTONACO ESTERNO E SOSTITUZIONE INFISSI ESISTENTI.
Implementation indicator
Superficie oggetto di intervento
- Target
- 537 mq
- Achieved
- 537 mq
Download project
Funding monitored
€ 148,067.60
of which cohesion funds
€ 74,033.80
Given name | Amount |
---|---|
Development and Cohesion Fund | 74033.80 |
Another public source | 74033.80 |
- Economies:
- € 1,932.40
Payments monitored
€ 148,067.60
of which cohesion funds
€ 74,033.80
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2019 | 147203.12 | 147203.12 | 99 |
2020 | 0 | 147203.12 | 99 |
2021 | 864.48 | 148067.60 | 100 |
State of progress
Completed
Expected start: 03/04/2019
Effective start: 03/04/2019
Expected end: 22/08/2019
Effective end: 22/08/2019
Entities
- Planning body
- REGIONE MOLISE
- Implementing body
- DIOCESI DI TERMOLI-LARINO
- Beneficiary
- DIOCESI DI TERMOLI-LARINO
- Executor
- COST CAM S.R.L.
Programming area
- Programme
- PSC REGIONE MOLISE
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Cohesion funds
- € 74,033.80
- Payments on cohesion funds
- € 74,033.80
- Policy Area
- Cultura
- Sector of intervention
- Patrimonio e paesaggio