CUP: B57D17000010006
LAVORI DI COMPLETAMENTO, RISTRUTTURAZIONE, MESSA IN SICUREZZA E RIQUALIFICAZIONE DEGLI IMPIANTI SPORTIVI E STRUTTURE RICETTIVE - COMPLESSO SPORTIVO MULTIFUNZIONALE AL CONVENTO
SUMMARY OF THE PROJECT
RIQUALIFICAZIONE DEGLI IMPIANTI SPORTIVI E STRUTTURE RICETTIVE - COMPLESSO SPORTIVO MULTIFUNZIONALE AL CONVENTO SANTA MARIA DELLA LIBERA
Implementation indicator
Superficie oggetto di intervento
- Target
- 9,450 mq
- Achieved
- 0 mq
Download project
Funding monitored
€ 451,149.89
of which cohesion funds
€ 338,362.42
Given name | Amount |
---|---|
Development and Cohesion Fund | 338362.42 |
Municipality | 112787.47 |
- Economies:
- € 28,850.11
Payments monitored
€ 238,274.69
of which cohesion funds
€ 178,706.01
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2020 | 79700.34 | 79700.34 | 17 |
2021 | 79924.01 | 159624.35 | 35 |
2022 | 1020.00 | 160644.35 | 35 |
2023 | 0 | 160644.35 | 35 |
2024 | 77630.34 | 238274.69 | 52 |
State of progress
Open
Expected start: 18/03/2020
Effective start: 18/03/2020
Expected end: 30/06/2025
Effective end: not available
Entities
- Planning body
- REGIONE MOLISE
- Implementing body
- COMUNE DI CERCEMAGGIORE
- Beneficiary
- COMUNE DI CERCEMAGGIORE
- Executor
- TECNOCOSTRUZIONI S.R.L.
Programming area
- Programme
- PSC REGIONE MOLISE
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Cohesion funds
- € 338,362.42
- Payments on cohesion funds
- € 178,706.01
- Policy Area
- Riqualificazione urbana
- Sector of intervention
- Edilizia e spazi pubblici
Other projects in territory
Same theme
Same type of investment
RECUPERO DI IMMOBILE A FINI AMBIENTALI | € 1,022,767 |
INTERVENTI DI RIQUALIFICAZIONE DELL'AREA SANTA MARIA A MONTE E DEL MANUFATTO DESTINATO AD ATTIVITA' TURISTICO RICREATIVE | € 33,893 |