RIQUALIFICAZIONE E COMPLETAMENTO DEL COMPLESSO SPORTIVO COMUNALE
SUMMARY OF THE PROJECT
RIQUALIFICAZIONE E COMPLETAMENTO DEL COMPLESSO SPORTIVO COMUNALE
Implementation indicator
Superficie oggetto di intervento
- Target
- 6,800 mq
- Achieved
- 6,800 mq
Download project
Funding monitored
€ 243,007.40
of which cohesion funds
€ 194,405.92
Given name | Amount |
---|---|
Development and Cohesion Fund | 194405.92 |
Municipality | 48601.48 |
- Economies:
- € 6,992.60
Payments monitored
€ 243,007.40
of which cohesion funds
€ 194,405.92
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2019 | 12904.02 | 12904.02 | 5 |
2020 | 230103.38 | 243007.40 | 100 |
State of progress
Completed
Expected start: 23/08/2019
Effective start: 23/08/2019
Expected end: 13/08/2020
Effective end: 27/10/2020
Entities
- Planning body
- REGIONE MOLISE
- Implementing body
- COMUNE DI SEPINO
- Beneficiary
- COMUNE DI SEPINO
- Executor
- DE DONA GIUSEPPE SRL
Programming area
- Programme
- PSC REGIONE MOLISE
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Cohesion funds
- € 194,405.92
- Payments on cohesion funds
- € 194,405.92
- Policy Area
- Riqualificazione urbana
- Sector of intervention
- Edilizia e spazi pubblici
Other projects in territory
Same theme
Same type of investment
INTERVENTI DI EFFICIENZA ENERGETICA NEGLI EDIFICI PUBBLICI-SEPINO | € 76,800 |