INTERVENTO A - RETE IDRICA
SUMMARY OF THE PROJECT
MANUTENZIONE STRAORDINARIA E POTENZIAMENTO DELLA RETE IDRICA DEL CONSORZIO PER LO SVILUPPO INDUSTRIALE ISERNIA-VENAFRO
Implementation indicator
Popolazione addizionale servita dall'approvvigionamento idrico potenziato
- Target
- 500 num
- Achieved
- 0 num
Funding monitored
€ 1,600,000.00
of which cohesion funds
€ 1,600,000.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 1600000.00 |
Payments monitored
€ 173,815.69
of which cohesion funds
€ 173,815.69
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2022 | 600.00 | 600.00 | 0 |
2023 | 173215.69 | 173815.69 | 10 |
State of progress
Open
Expected start: 04/05/2023
Effective start: 04/05/2023
Expected end: 31/10/2024
Effective end: not available
Entities
- Planning body
- REGIONE MOLISE
- Implementing body
- CONSORZIO PER LO SVILUPPO INDUSTRIALE ISERNIA VENAFRO
- Beneficiary
- CONSORZIO PER LO SVILUPPO INDUSTRIALE ISERNIA VENAFRO
- Executor
-
FACCIOLINI S.R.L.
ELETTRICA MATER DI TOMEO TERENZIO & C. SNC
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- PSC REGIONE MOLISE
- Policy Area
- Ambiente e risorse naturali
- Sector of intervention
- Risorse idriche
Other projects in territory
Same theme
Same type of investment
SISTEMAZIONE DELLA CADUTA MASSI LUNGO LA SP N. 13 PER SANTA MARIA OLIVETO. - COMUNE DI POZZILLI - IS | € 250,000 |