CUP: B57B12000050001
LAVORI DI RICOSTRUZIONE IMMOBILI PRIVATI IN CLASSE DI PRIORIT AAA PEU 76 SP 1
SUMMARY OF THE PROJECT
LAVORI DI RICOSTRUZIONE IMMOBILI PRIVATI IN CLASSE DI PRIORIT AAA PEU 76 SP 1
Implementation indicator
Volume oggetto di intervento
- Target
- 345.58 mc
- Achieved
- 345.58 mc
Download project
Funding monitored
€ 57,420.98
of which cohesion funds
€ 57,420.98
Given name | Amount |
---|---|
Development and Cohesion Fund | 57420.98 |
- Economies:
- € 17.68
Payments monitored
€ 57,420.98
of which cohesion funds
€ 57,420.98
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2008 | 385.00 | 385.00 | 0 |
2009 | 0 | 385.00 | 0 |
2010 | 0 | 385.00 | 0 |
2011 | 0 | 385.00 | 0 |
2012 | 0 | 385.00 | 0 |
2013 | 0 | 385.00 | 0 |
2014 | 0 | 385.00 | 0 |
2015 | 0 | 385.00 | 0 |
2016 | 48119.84 | 48504.84 | 84 |
2017 | 0 | 48504.84 | 84 |
2018 | 8916.14 | 57420.98 | 100 |
State of progress
Completed
Expected start: 24/07/2015
Effective start: 24/07/2015
Expected end: 09/01/2017
Effective end: 09/01/2017
Entities
- Planning body
- REGIONE MOLISE
- Implementing body
- COMUNE DI CERCEMAGGIORE
- Beneficiary
- CONSORZIO PEU 76 (COMUNE DI CERCEMAGGIORE)
Programming area
- Programme
- PSC REGIONE MOLISE
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Cohesion funds
- € 57,420.98
- Payments on cohesion funds
- € 57,420.98
- Policy Area
- Ambiente e risorse naturali
- Sector of intervention
- Rischi e adattamento climatico