CUP: F87B11000090008
lavori di ricostruzione immobili privati in classe di priorit AAA PEU 73 Sp 1
SUMMARY OF THE PROJECT
lavori di ricostruzione immobili privati in classe di priorit AAA PEU 73 Sp 1
Implementation indicator
Volume oggetto di intervento
- Target
- 2,257.39 mc
- Achieved
- 2,257.39 mc
Download project
Funding monitored
€ 367,467.53
of which cohesion funds
€ 367,467.53
Given name | Amount |
---|---|
Development and Cohesion Fund | 367467.53 |
- Economies:
- € 1,861.98
Payments monitored
€ 367,467.53
of which cohesion funds
€ 367,467.53
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2007 | 2755.63 | 2755.63 | 0 |
2008 | 0 | 2755.63 | 0 |
2009 | 0 | 2755.63 | 0 |
2010 | 0 | 2755.63 | 0 |
2011 | 0 | 2755.63 | 0 |
2012 | 0 | 2755.63 | 0 |
2013 | 0 | 2755.63 | 0 |
2014 | 0 | 2755.63 | 0 |
2015 | 0 | 2755.63 | 0 |
2016 | 0 | 2755.63 | 0 |
2017 | 99357.86 | 102113.49 | 27 |
2018 | 144324.03 | 246437.52 | 67 |
2019 | 0 | 246437.52 | 67 |
2020 | 0 | 246437.52 | 67 |
2021 | 0 | 246437.52 | 67 |
2022 | 121030.01 | 367467.53 | 100 |
State of progress
Completed
Expected start: 12/11/2015
Effective start: 12/11/2015
Expected end: 26/05/2021
Effective end: 26/05/2021
Entities
- Planning body
- REGIONE MOLISE, GIUNTA REGIONALE
- Implementing body
- COMUNE DI MONTORIO NEI FRENTANI
- Beneficiary
- Consorzio PEU 73 (Comune di Montorio nei Frentani)
Programming area
- Programme
- PSC REGIONE MOLISE
- 2007-2013 National Development and Cohesion Fund
- 2007-2013 National Development and Cohesion Fund
- Cohesion funds
- € 367,467.53
- Payments on cohesion funds
- € 367,467.53
- Policy Area
- Ambiente e risorse naturali
- Sector of intervention
- Rischi e adattamento climatico