CUP: I93F07000250009
lavori di ricostruzione immobili privati in classe di priorit AAA PEU 73 Sp 1
SUMMARY OF THE PROJECT
lavori di ricostruzione immobili privati in classe di priorit AAA PEU 73 Sp 1
Implementation indicator
Volume oggetto di intervento
- Target
- 890.13 mc
- Achieved
- 890.13 mc
Download project
Funding monitored
€ 130,192.00
of which cohesion funds
€ 130,192.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 130192.00 |
Payments monitored
€ 130,192.00
of which cohesion funds
€ 130,192.00
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2007 | 1123.26 | 1123.26 | 0 |
2008 | 0 | 1123.26 | 0 |
2009 | 0 | 1123.26 | 0 |
2010 | 0 | 1123.26 | 0 |
2011 | 0 | 1123.26 | 0 |
2012 | 0 | 1123.26 | 0 |
2013 | 0 | 1123.26 | 0 |
2014 | 0 | 1123.26 | 0 |
2015 | 0 | 1123.26 | 0 |
2016 | 0 | 1123.26 | 0 |
2017 | 0 | 1123.26 | 0 |
2018 | 66720.38 | 67843.64 | 52 |
2019 | 0 | 67843.64 | 52 |
2020 | 62348.36 | 130192.00 | 100 |
State of progress
Completed
Expected start: 21/09/2015
Effective start: 21/09/2015
Expected end: 19/12/2018
Effective end: 19/12/2018
Entities
- Planning body
- REGIONE MOLISE, GIUNTA REGIONALE
- Implementing body
- COMUNE DI COLLETORTO
- Beneficiary
- Consorzio PEU 73 (Comune di Colletorto)
Programming area
- Programme
- PSC REGIONE MOLISE
- 2007-2013 National Development and Cohesion Fund
- 2007-2013 National Development and Cohesion Fund
- Cohesion funds
- € 130,192.00
- Payments on cohesion funds
- € 130,192.00
- Policy Area
- Ambiente e risorse naturali
- Sector of intervention
- Rischi e adattamento climatico